Why Choose Hechang Optical?
HECHANG Optical supports eyewear brands, wholesalers, and OEM/ODM customers with product development, customization, manufacturing, and quality-control services.
Our team works with customers from product design and sampling through production and inspection, helping each project follow the confirmed specifications and manufacturing requirements.
First Article Inspection in HECHANG Optical's Eyewear Manufacturing Process
During eyewear production, changes in design, materials, equipment, processes, parameters, personnel, or production conditions can affect subsequent production.
HECHANG Optical uses first article inspection (FAI) at defined production stages, including initial production, after relevant process changes, and when production resumes after certain stoppages. The purpose is to verify that the first products meet the applicable requirements before subsequent production proceeds.
01
Definition of First Article and First Article Inspection by HECHANG Optical
Process Changes
During production, changes may occur in the 5M1E factors: man, machine, material, method, environment, and measurement. These can include personnel changes, equipment adjustments or maintenance, material changes, fixture modifications, design changes, or production stoppages.
First Article
A first article refers to the initial product or first few products produced at the start of a production shift or after a relevant process change. Depending on the production or customer requirements, multiple consecutive samples may be used for first article verification.
First Article Inspection
First article inspection (FAI) is the inspection of the initial product or first few products produced at the start of a shift or after a relevant process change.
At HECHANG Optical, at least 3–5 consecutive products are typically inspected. Subsequent production proceeds only after the required first article inspection has been completed and the inspected products meet the applicable requirements.
02
Purpose of First Article Inspection by HECHANG Optical
First article inspection is used to identify potential production issues before subsequent batch production proceeds, helping reduce the risk of repeated non-conformities, rework, and material waste.
The purpose of FAI is to verify that the initial products meet the applicable drawings, specifications, process requirements, or approved samples before continued production.
FAI can help identify issues such as tool wear, incorrect installation, reduced measurement accuracy, misinterpretation of drawings, or incorrect material or formula inputs. When an issue is identified, corrective action can be taken and the first article re-inspected before production continues.
03
When to Conduct First Article Inspection by HECHANG Optical
At the Start of Each Work Shift
FAI is conducted at the start of a work shift before regular production proceeds.
Operator Changes
When the personnel operating relevant equipment change, FAI is performed to verify the first products produced under the new operating conditions.
Equipment or Tool Changes or Adjustments
FAI is required after relevant equipment or tooling changes, such as tool replacement, re-sharpening, or adjustment.
Changes in Technical Specifications, Processes, or Parameters
Changes such as revised surface roughness requirements, switching from reaming to boring of inner holes, or adjustments to CNC program feed rates or speeds require FAI to verify the resulting product against the applicable requirements.
Use of New or Substitute Materials
When new or substitute materials are introduced, FAI is performed to verify the resulting product against the specified requirements.
Replacement or Re-analysis of Chemical Solutions
FAI is also required when relevant process solutions are replaced or re-analyzed, including bath solutions used in processes such as phosphating or nitriding.
04
First Article Inspection Process by HECHANG Optical
HECHANG Optical uses a three-step first article inspection process: self-inspection, peer inspection, and specialist inspection.
Self-Inspection
The operator first checks the product and corrects any obvious issues identified at this stage.
Peer Inspection
After self-inspection, the product is checked by the team leader or a colleague as an additional verification step.
Specialist Inspection
A dedicated quality inspector then verifies the product against the applicable drawings, specifications, process requirements, or approved samples. Subsequent production proceeds only after the first article passes the required inspection and approval.
After approval, the first article is marked with the required identifier, including a "√" where applicable, and retained until the end of the shift or production batch as a reference sample.
If the first article does not pass inspection, the cause is identified, corrective action is taken, and the product is reworked or reprocessed as appropriate. The inspection sequence is then repeated until the first article meets the applicable requirements.
05
Key Items in First Article Inspection by HECHANG Optical
During first article inspection, HECHANG Optical verifies key production and product requirements before subsequent production proceeds.
Drawing and Job Order Verification
Verify that the drawing number matches the applicable job order and product specifications.
Material, Blank, or Semi-Finished Product Verification
Verify that the material, blank, or semi-finished product matches the applicable job order requirements.
Surface Treatment and Positioning
Check the required surface treatment and positioning of materials or blanks against the applicable specifications.
Formula and Ingredient Verification
Verify that the applicable formulas and ingredients meet the specified requirements.
First Article Quality Characteristics
Verify that the first article meets the quality characteristics specified in the applicable drawings or technical documents.
06
First Article Inspection Standard Procedure by HECHANG Optical
Scope and Applicability
This section summarizes the requirements and procedures used for first article inspection (FAI) and batch first article inspection within HECHANG Optical's production process.
Responsibilities
Production Department
Production Line Supervisors
Inspectors
FAI Approval
Control Requirements
01
Initial Production
The first completed semi-finished or finished product produced at the start of applicable production must undergo first article inspection and confirmation before subsequent production proceeds.
02
Regular Production
For regular production, first article inspection is conducted on a batch-by-batch basis according to the applicable production requirements.
03
Resumption After Downtime
When production resumes after downtime caused by relevant equipment or process issues, first article inspection and confirmation are performed before subsequent production proceeds.
04
Material or Specification Changes
When relevant product materials or specifications are changed, first article inspection and confirmation are required before subsequent production proceeds.
05
New Product FAI
For new products, the production team notifies the relevant inspection personnel before FAI is conducted.
The first article is verified against the applicable drawings, lists, process documents, and other relevant product requirements. If the first article does not meet the applicable requirements, the issue is recorded and the product is returned for the required rework or correction before re-inspection.
Subsequent production proceeds only after the required first article inspection and confirmation have been completed.
06
Sample Retention
The first article used as the reference sample for mass production must be retained by the production department until the entire production batch is completed.
07
Material Compliance
During first article inspection (FAI), all raw materials and auxiliary materials used in production must be verified to confirm that they meet the specified requirements.
Procedure
01
Supervision During First Article Production
During first article production, the production line supervisor and inspectors monitor the on-site production process and verify that the applicable process documents are being followed.
If an issue is identified during production, the required correction is made before the first article proceeds to further inspection and confirmation.
02
Completion of Production Processes
For regular production and production resumed after downtime, the required production processes for the first article must be completed before FAI.
The responsible production personnel inspect the first article and sign the first article card before submitting it to the inspectors for further verification.
03
Conducting First Article Inspection
During FAI, the inspector and production line supervisor verify the first article against the applicable drawings, lists or customer-provided samples, process documents, and product requirements.
If the first article passes inspection, it is marked accordingly, such as "First Article Passed," and the first article card is signed by the responsible production personnel or representative and the inspector.
04
Handling Major Changes
When significant product changes require FAI, the relevant production personnel and inspectors complete the required inspection and sign-off.
If the first article does not pass inspection, it is returned for the required rework or correction and then re-inspected before production proceeds.
05
New Product and Changes
The first production batch of a new product, as well as semi-finished or finished products produced after relevant material or specification changes, must undergo the required first article inspection and confirmation before subsequent production proceeds.
06
Record Keeping
FAI results are documented as part of the inspection process, including completion of the applicable first article confirmation records or reports.
07
Addressing Quality Issues
If a quality issue or non-conformity is identified during first article production or inspection, the issue is reviewed and the required corrective action is taken before the product is rechecked.
Subsequent production proceeds only after the first article meets the applicable requirements, has been approved, and the inspection result has been recorded on the first article card.
08
Normal Inspection After FAI
Routine production inspection proceeds after the required first article inspection and confirmation have been completed.
Featured Eyewear Products
Explore selected eyewear products available for OEM, ODM, private-label, and wholesale projects.
Product options and customization details vary by style and project requirements.
Our Product Series
Sunglasses
Sports Glasses
Ski Goggles
Optical Glasses
Contact HECHANG Optical
Contact us to discuss your eyewear project, request samples, or arrange a factory visit to learn more about our manufacturing and quality-control capabilities.
For certain customized options, such as developing a specific color, the minimum order quantity is 300 units.
You can reach us by phone, email, or through the contact form below. Our team will respond within 24 hours.
Rest assured that your privacy is important to us, and all information provided will be handled with the utmost confidentiality.
Scan QR Code